DLR introduces new trains after safety recall and delays
The first of 54 new trains are now being reintroduced to service following a safety issue investigation.
Trust 44Craft 61Hype 20How this was reported ▾
The central claim is attributed to TfL, a named body, and a specific TfL officer is quoted.
How well corroborated and evidenced the reporting is. Higher is better.
The reporting clearly separates facts from comment and explains why the story matters to DLR users.
Context, balance and separation of fact from comment. Higher is better.
The headline accurately reflects the article's content without exaggeration.
How far presentation runs ahead of substance. Lower is better.
1 source assessed · methodology
The first of 54 new trains for the Docklands Light Railway (DLR) are now being introduced to London's transport network. These new trains feature live travel information, air conditioning, and mobile charging points.
Delays and Safety Recall
First new DLR train returns to service after modifications
The first of 54 new trains has resumed passenger journeys following a performance issue that led to their withdrawal.
The new DLR fleet was originally scheduled to arrive in April 2024, but its introduction was postponed until October 2025. Shortly after their initial deployment, the trains were recalled within a month due to a safety issue. Transport for London (TfL) stated that all trains were removed as a precaution while TfL and the manufacturer, CAF, investigated the problem and developed a solution. These modifications have now been completed, and the trains have undergone extensive testing.
I apologise for the delay in reintroducing the trains but am pleased this marks an important milestone in delivering a modern new fleet for the DLR.
Stuart Harvey, TfL's chief capital officer
Stuart Harvey, TfL's chief capital officer, apologised for the disruption caused by the delay in reintroducing the trains. He described the current reintroduction as an important milestone in delivering a modern fleet for the DLR.
Uber driver sues TfL over licence renewal delays
High court grants judicial review to Julius Mugabo who claims delays caused significant debt and fear of losing his home.
Phased Reintroduction
The phased reintroduction of the fleet will commence on the Stratford International to Woolwich Arsenal route. TfL indicated that more trains will be gradually added to the network as the reintroduction progresses.
Questions this report answers
+When were the new DLR trains originally expected?
The new DLR trains were originally due to arrive in April 2024. However, their introduction was delayed, with the fleet's arrival eventually scheduled for October 2025.
+Why were the new DLR trains recalled?
The new DLR trains were recalled within a month of their introduction due to a safety issue that was discovered. Transport for London and the manufacturer CAF investigated the problem and completed necessary modifications.
+Where will the new DLR trains be introduced first?
The phased reintroduction of the new DLR trains will begin on the route between Stratford International and Woolwich Arsenal. Transport for London plans to gradually introduce more trains to the network thereafter.