London Travel News reportProjectsWest LondonFile OLD-OAK-

Old Oak Common HS2 platforms finished but conventional rail delayed to 2029

Residents near the West London station face eight more years of construction disruption before full services begin

Trust 42Craft 55Hype 15How this was reported ▾
Trust42/100

Only one named source, no independent corroboration.

How well corroborated and evidenced the reporting is. Higher is better.

Craft55/100

Quotes given but no affected residents or opposition voices.

Context, balance and separation of fact from comment. Higher is better.

Hype15/100

Proportionate language, headline matches content.

How far presentation runs ahead of substance. Lower is better.

1 source assessed · methodology

NewsroomLTN
Newsroom signatureLondon Travel DeskOperator data, editor-supervised
Filed London TravelStatus checked against the operator
Pass this story on
Old Oak Common HS2 platforms finished but conventional rail delayed to 2029
HNL visual fileWest London

HS2 has completed construction of six 450-metre platforms at Old Oak Common station in West London, marking a milestone for the project. The platforms, built using 1,946 pre-cast concrete slabs, will serve high-speed trains when the station opens. However, conventional rail services, including the Elizabeth line and Great Western Main Line, will not begin until 2029 due to a planned blockade to Paddington.

Construction challenges and delays

Read Next in London Travel News4 min read
HS2 plaque marks Brunel legacy 40 metres beneath Kensal Green

HS2 plaque marks Brunel legacy 40 metres beneath Kensal Green

Heritage installation inside Euston Tunnel honours tunnelling pioneers Sir Marc and Isambard Kingdom Brunel

The platforms were assembled from slabs manufactured in the East Midlands, each weighing between four and five tonnes. Teams worked from both ends of the site, meeting in the middle to form three island-style blocks. A void beneath the platforms allows for electrical and service installations. HS2’s station construction partner, Balfour Beatty Vinci Systra (BBVS), oversaw the work, which included pouring concrete for 1.59-metre-high invert walls.

Recent heatwaves forced adjustments to the construction schedule. HS2 senior project manager Russell D’Urso said teams began concrete pours earlier in the day and reduced volumes to manage the extreme temperatures. BBVS project director Steve O’Sullivan added that temporary structures and safety monitoring were required to prevent the walls from collapsing during excavation.

Tunnel progress and future phases

Related Borough Coverage5 min read
London transport deputy mayor to outline climate plans at Manchester conference

London transport deputy mayor to outline climate plans at Manchester conference

Seb Dance will speak on adapting London’s infrastructure to warmer weather at the ICE Resilient Transport event on 23 September 2026

Two tunnel boring machines (TBMs) launched from Old Oak Common earlier this year are expected to reach Euston by 2027. The machines will connect the station to HS2’s central London terminus. Skanska Costain Strabag (SCS), HS2’s London tunnels contractor, is set to break through the west wall of the underground box by November, though some on-site workers believe this could happen sooner.

Work on the conventional platforms has already started but cannot be completed until a 12-day blockade to Paddington is implemented. HS2 project client director Dave Lock said negotiations with Network Rail are ongoing, with the blockade not expected before 2029. The blockade will allow the existing Great Western Main Line track to be realigned to reach the new station.

What happens next for residents

Construction at Old Oak Common will continue, with the first part of the station’s roof scheduled for installation in early 2027. BBVS area manager Lucy Craggs said the project has provided learning opportunities for young engineers, with skills developed on-site being shared with the Euston development team. The station’s completion remains dependent on the 2029 blockade, which will finalise the conventional rail connections.

1,946Pre-cast slabs used to build the platformsEach slab weighs between 4-5 tonnes and was manufactured in the East Midlands

Questions this report answers

+When will Old Oak Common station open for conventional rail services?

Conventional rail services, including the Elizabeth line and Great Western Main Line, will not start until 2029. A 12-day blockade to Paddington is required to realign tracks, and this is not expected before then.

+How long are the new HS2 platforms at Old Oak Common?

The six high-speed platforms at Old Oak Common are each 450 metres long. They were built using 1,946 pre-cast concrete slabs, with construction completed in August 2026.

+When will the tunnel boring machines reach Euston?

Two tunnel boring machines launched from Old Oak Common are expected to reach Euston by 2027. They will connect the station to HS2’s central London terminus, with breakthrough anticipated next year.

+What disruption will residents near Old Oak Common face in the coming years?

Residents on Old Oak Common Lane will see continued construction until at least 2029. The station’s roof will be installed in early 2027, and the 12-day blockade to Paddington will cause further disruption before full services begin.

On the recordHOW
WE FILE

No invented reporter. No hidden source trail.

The London Travel Desk assembled this report from the outlets listed below. Language-model drafting is reviewed under human editorial supervision, with scoring notes and corrections kept visible.

More Coverage in Projects

HS2 plaque marks Brunel legacy 40 metres beneath Kensal Green

HS2 plaque marks Brunel legacy 40 metres beneath Kensal Green

North London | 4 min read
London transport deputy mayor to outline climate plans at Manchester conference

London transport deputy mayor to outline climate plans at Manchester conference

London | 5 min read
London Cable Car reveals east London’s landmarks from 90 metres up

London Cable Car reveals east London’s landmarks from 90 metres up

East London | 5 min read
£7m Sydenham cable project tunnels under railway without stopping trains

£7m Sydenham cable project tunnels under railway without stopping trains

South London | 4 min read

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.

Old Oak Common HS2 platforms finished but conventional rail delayed to 2029 | London Travel News