HS2 tunnel boring machines reach halfway point to Euston
Karen and Madeleine have completed 2.25 miles of the 4.5-mile journey from Old Oak Common.
Trust 30Craft 60Hype 20How this was reported ▾
The central claim is attributed to HS2's chief executive, but no documents or independent sources are cited.
How well corroborated and evidenced the reporting is. Higher is better.
The article clearly separates fact from comment and provides specific details about the tunnelling process and timeline.
Context, balance and separation of fact from comment. Higher is better.
The language used is measured and proportionate, with no sensationalism or manufactured urgency.
How far presentation runs ahead of substance. Lower is better.
2 sources assessed · methodology
Two tunnel boring machines (TBMs) digging HS2 tunnels towards Euston have now completed half of their 4.5-mile route. The machines, named Karen and Madeleine, have drilled 2.25 miles from their launch site at Old Oak Common. They are currently situated between West Hampstead and Kilburn High Road stations.
Tunnelling progress and timeline
Vauxhall Bridge faces closure without £60m repairs
Transport for London has applied to a government fund for investment to prevent restrictions on buses and fire engines within four years.
Karen and Madeleine began their work in January and March 2026 respectively. Operating continuously, the TBMs advance approximately 16 metres each day. The tunnelling operation is anticipated to conclude in 2027, with the machines stopping their work on the approach to Euston station, the planned central London terminus for HS2.
As they excavate, the TBMs install precast concrete segments to line the tunnels. A total of 48,294 such segments are required for the Euston tunnels. These segments are being manufactured in Hartlepool. The tunnelling process is expected to yield around 1.5 million tonnes of excavated material. This material is transported back to Old Oak Common before being sent by rail for landscaping purposes at other sites.
Once the tunnelling is finished, workers will dismantle the TBMs. Most of the machinery will be removed through the completed tunnels. The wide cutting heads, measuring 8.53 metres, will initially remain buried. They are intended to be released for disposal when the large Euston cavern is constructed adjacent to the tunnel. However, the steel can shields at the front of the machines will be permanently installed and will form part of the HS2 railway tunnel structure.
Twickenham Road Blocked by Emergency Incident
Queues are forming on the busy thoroughfare following the incident.
Reaching the halfway mark for building the programme’s last deep bored tunnel is a magnificent achievement by everyone involved. Their work driving the high speed line into central London is fundamental to the long term ambition of increasing the prosperity of the area around Euston.
Mark Wild, HS2 chief executive
The tunnelling operation is managed by HS2's London tunnelling contractor, the Skanska Costain STRABAG joint venture.
Questions this report answers
+How far have the HS2 tunnel boring machines travelled?
The two tunnel boring machines, Karen and Madeleine, have completed 2.25 miles of their 4.5-mile journey towards Euston. They launched from Old Oak Common in early 2026 and are expected to finish their tunnelling work in 2027.
+When is the tunnelling expected to be finished?
The tunnelling work by machines Karen and Madeleine is expected to be completed in 2027. They will stop underground on the approach to Euston station, where HS2's central London terminus is planned.
+What materials are being used to build the tunnels?
The tunnels will require 48,294 precast concrete segments, which are being manufactured in Hartlepool. The tunnelling process is also expected to generate approximately 1.5 million tonnes of excavated material.