Lower Thames Crossing uses Europe's largest tunnel boring machine

The £11bn project aims to double road capacity east of London and remove the Dartford Crossing bottleneck.

Trust 44Craft 67Hype 45How this was reported ▾
Trust44/100

The central claim is attributed to named individuals and bodies, but lacks direct quotes from official documents or datasets.

How well corroborated and evidenced the reporting is. Higher is better.

Craft67/100

The article explains why the project matters, names those involved, and separates fact from comment.

Context, balance and separation of fact from comment. Higher is better.

Hype45/100

The headline uses moderate language, and the article focuses on the project's green ambitions.

How far presentation runs ahead of substance. Lower is better.

1 source assessed · methodology

NewsroomLTN
Newsroom signatureLondon Travel DeskOperator data, editor-supervised
Filed London TravelStatus checked against the operator
Pass this story on
Lower Thames Crossing uses Europe's largest tunnel boring machine
HNL visual fileLondon

Construction has begun on the Lower Thames Crossing, a project that will feature the largest tunnel boring machine (TBM) ever used in Europe. This machine, with a diameter of 16.4 metres, is being built by Herrenknecht and is scheduled to commence operations in 2028. The £11bn project, which started enabling works in March, is set to create a new 23km route connecting Kent and Essex via twin tunnels beneath the River Thames.

The primary objectives of the Lower Thames Crossing are to improve connectivity throughout the South East of England. This includes increasing logistics capacity on the road network, doubling the road capacity across the Thames east of London, and eliminating the significant congestion at the Dartford Crossing. The project is described as transformational due to its scale and its ambitious environmental goals.

Read Next in London Travel News3 min read
A2 and M25 face overnight closures September 14-17

A2 and M25 face overnight closures September 14-17

National Highways plans roadworks affecting both carriageways and slip roads during late evening and early morning hours.

Focus on Green Construction

National Highways designated the Lower Thames Crossing as a carbon pathfinder project in 2022, a move that has led to its description as "the UK’s greenest road." Key ambitions include reducing the construction carbon footprint by 70% compared to traditional methods and offsetting the remaining emissions to achieve carbon-neutral construction. This aligns with standards such as PAS 2080. The project has also successfully eliminated diesel from its worksites by utilising electric plant, green hydrogen, and biofuel.

Lower Thames Crossing chief executive officer Matt Palmer stated that the project aims to demonstrate that infrastructure can be delivered sustainably. He noted that in 2022, while other major projects like Hinkley Point C and HS2 were underway, the Lower Thames Crossing was a road project in Essex. To attract skilled contractors and talent, the project needed to adopt a distinctive approach.

Related Borough Coverage4 min read
Engineers Criticise National Highways' Drainage Design Rules

Engineers Criticise National Highways' Drainage Design Rules

Firms say the Design Palette lacks guidance and contains factual errors, potentially compromising water quality.

The project was the first major UK scheme to have a legally binding carbon footprint limit as part of its Development Consent Order. Carbon considerations played a significant role in the tender evaluation for key delivery partners, including Bouygues Travaux Publics, Murphy Joint Venture (BMJV) for tunnels and approaches, Balfour Beatty for roads north of the Thames, and Skanska for roads in Kent.

Programme director Shaun Pidcock highlighted the importance of early design thinking in establishing green construction practices. Embedding sustainability principles from the project's inception helped to reduce embodied carbon before site activities commenced. The project set an industry target for carbon usage, then aimed to reduce it by 30% below a reference line, inviting delivery partners to bid on this basis.

Early design decisions included opting for a single TBM for the bored tunnels, which reduced the embodied carbon associated with manufacturing and transporting equipment. This also necessitated a smaller scale for associated facilities like the precast segment factory and wastewater treatment plant. Antoine Schwob, BMJV project director for tunnels and approaches, commented that the project had "no other choice than to really push boundaries into delivering low-carbon solutions."

Skanska senior design lead Max Cochrane explained that emphasis has been placed on integrating design choices since the contract began two and a half years ago. Construction methodology and design solutions are now fixed, with detailed design progressing rapidly. Low-carbon design principles have also been applied to key structures, such as a planned footbridge over the A127, with potential for wider application across the road network.

Low Carbon Materials and Plant

The selection of low-carbon materials and plant, including steel, concrete, and machinery, aligns with the project's green design principles. Heidelberg Materials is supplying evoBuild low-carbon concrete, which incorporates up to 70% cement replacement using ground granulated blast furnace slag, and evoZero near-zero cement. Ian Innes, Heidelberg Materials UK major project key account director, noted that reducing cement's carbon impact is a key industry driver.

The project team is collaborating with UK green hydrogen producer GeoPura. In October, a British-made JCB hydrogen-fuelled digger, the first used outside a test environment globally, was deployed for survey work in Kent. The scheme is on track to become the world's largest zero-emissions machinery site, with an estimated 150 zero-emissions machines planned, ranging from 20-tonne diggers to rollers and telehandlers.

Lower Thames Crossing is also working with electric construction machinery manufacturers such as Volvo Construction Equipment. Kent Sahlin, Volvo's global product manager for wheel loaders, confirmed the manufacturer has offered the scheme its A40 electric articulated haulers, capable of carrying 39 tonnes, for large-scale material movements. Volvo's electric range includes smaller articulated haulers, excavators, wheel loaders, material handlers, and trucks.

Questions this report answers

+What is the main purpose of the Lower Thames Crossing project?

The Lower Thames Crossing project aims to significantly improve connectivity across the South East by doubling the cross-river road capacity east of London. It also intends to remove the long-standing bottleneck at the Dartford Crossing, facilitating smoother traffic flow.

+How is the Lower Thames Crossing addressing environmental concerns during construction?

The project is designated as a carbon pathfinder, aiming to cut its construction carbon footprint by 70% and achieve carbon-neutral construction. It has removed diesel from worksites by using electric plant, green hydrogen, and biofuel, and has a legally binding carbon footprint limit.

+What is the significance of the tunnel boring machine being used?

The project is utilising Europe's largest tunnel boring machine, with a diameter of 16.4 metres. This machine is scheduled to begin work in 2028 and is a key component in constructing the new 23km twin tunnels beneath the River Thames.

On the recordHOW
WE FILE

No invented reporter. No hidden source trail.

The London Travel Desk assembled this report from the outlets listed below. Language-model drafting is reviewed under human editorial supervision, with scoring notes and corrections kept visible.

More Coverage in Roads & Driving

A2 and M25 face overnight closures September 14-17

A2 and M25 face overnight closures September 14-17

London | 3 min read
Engineers Criticise National Highways' Drainage Design Rules

Engineers Criticise National Highways' Drainage Design Rules

M25 | 4 min read
M25 Closed Anticlockwise After Lorry Crash

M25 Closed Anticlockwise After Lorry Crash

London | 1 min read
Marylebone Road Fire Shuts Major London Route

Marylebone Road Fire Shuts Major London Route

London | 2 min read

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.

Lower Thames Crossing £11bn project | London Travel News