Tyburn RWC Limited seeks permission for a 100,000 sq m development that would demolish three locally listed buildings.

Trust 42Craft 60Hype 20How this was reported ▾
Trust42/100

The central claim is attributed to a named body, but no other sources or documents are cited.

How well corroborated and evidenced the reporting is. Higher is better.

Craft60/100

The article explains why the story matters, names specific figures and dates, and states what happens next.

Context, balance and separation of fact from comment. Higher is better.

Hype20/100

The language used is measured and proportionate, with no sensationalism or manufactured urgency.

How far presentation runs ahead of substance. Lower is better.

1 source assessed · methodology

NewsroomLTN
Newsroom signatureLondon Travel DeskOperator data, editor-supervised
Filed London TravelStatus checked against the operator
Pass this story on
Data centre proposed for Charlton Riverside industrial land
HNL visual fileSouth London

A proposal for a substantial data centre has been put forward for industrial land at Charlton Riverside in south-east London. Real estate business Tyburn RWC Limited is behind the plan, which would see a 100,000 square metre development constructed on the site between the River Thames and Woolwich Road.

The proposed facility, which includes generator yards, a substation, and offices, would cover 100,000 sq m, an area equivalent to approximately 14 football pitches. The main data centre building itself would occupy 75,000 sq m of this space. This development comes shortly after plans were announced for thousands of new homes and jobs in the same area, a partnership involving Greenwich Council, Transport for London, and the mayor's office.

Read Next in London Travel News3 min read
Vineyard established at Denmark Hill station

Vineyard established at Denmark Hill station

Volunteers from the Camberwell Society have planted Bacchus vines on a south-facing embankment.

Impact on heritage buildings

To make way for the data centre, three buildings that are locally listed and form part of the Stone Foundries site would need to be demolished. Planning documents submitted by the applicant estimate that the demolition, excavation, and construction phases of the project would generate 64,086 tonnes of waste. The applicant states that 89% of this waste would be recycled.

Next steps for the proposal

Related Borough Coverage4 min read
Wandsworth Roundabout adverts to be raised on timber trellis despite 80 objections

Wandsworth Roundabout adverts to be raised on timber trellis despite 80 objections

Residents cite design and road safety concerns as council considers replacing metal loops with taller structure

Tyburn RWC Limited has submitted a request for an Environmental Impact Assessment Scoping Opinion to Greenwich Council, rather than a full planning application at this stage. The council has a deadline of 11 September to provide its response to this request. A full planning application is anticipated by the applicant to follow soon after the scoping opinion is issued.

The applicant estimates that if planning permission is granted, construction of the data centre would occur between 2028 and 2033, according to information provided to the Local Democracy Reporting Service.

Questions this report answers

+What is being proposed for Charlton Riverside?

Tyburn RWC Limited has proposed a large data centre development covering 100,000 square metres on industrial land at Charlton Riverside. The main building would be 75,000 square metres.

+What buildings will be demolished for the data centre?

Three buildings that are locally listed and are part of the Stone Foundries site would be demolished to make way for the proposed data centre development.

+When might the data centre be built?

The applicant, Tyburn RWC Limited, estimates that if planning permission is granted, construction of the data centre would take place between 2028 and 2033.

+What is the deadline for Greenwich Council regarding the proposal?

Greenwich Council has until 11 September to respond to Tyburn RWC Limited's request for an Environmental Impact Assessment Scoping Opinion for the proposed data centre.

On the recordHOW
WE FILE

No invented reporter. No hidden source trail.

The London Travel Desk assembled this report from the outlets listed below. Language-model drafting is reviewed under human editorial supervision, with scoring notes and corrections kept visible.

More Coverage in Projects

Vineyard established at Denmark Hill station

Vineyard established at Denmark Hill station

South London | 3 min read
Wandsworth Roundabout adverts to be raised on timber trellis despite 80 objections

Wandsworth Roundabout adverts to be raised on timber trellis despite 80 objections

South London | 4 min read
Wandsworth Roundabout advertising tower faces replacement after 133 objections

Wandsworth Roundabout advertising tower faces replacement after 133 objections

South London | 4 min read
Woolwich Free Ferry to stay free after TfL confirms no fare plans

Woolwich Free Ferry to stay free after TfL confirms no fare plans

South London | 5 min read

Who else reported this

Our article above is written from the facts in these reports. Read the originals — every one is linked.

Charlton Riverside data centre proposed | London Travel News